South Van Ness and Mission Intersection Closure August 4-9

South Van Ness and Mission Intersection Closure August 4-9
By John Gravener

With the recent completion of the new red transit lanes along Van Ness Avenue, the Van Ness Improvement Project is now focused on its upcoming Mission Street closure as the project works to complete construction later this year. 

The major intersection closure, scheduled for August 4-9, is planned to reduce the duration of the work there. By closing the full intersection for five days, the team can complete work in the intersection that would normally require two months of work completed one segment at a time. The goal is to minimize inconvenience for the public.

Map of Van Ness Avenue and Mission Street intersection showing detours and street closures. Streets closed to traffic include South Van Ness Avenue south of Market, Mission Street one block west of 11th Street, 12th Street north of Howard, South Van Ness north of Highway 101, Highway 101/Mission Street highway exit, and 12th Street south of Market will all be closed to traffic. Detour streets include Howard Street, Folsom Street, 10th Street, 9th Street, 13th Street, Duboce Avenue, Gough Street, Franklin Street, Fell Street, Hayes Street and Grove Street can all help you avoid the closed intersection.Map of Van Ness Avenue and Mission Street intersection with reroutes.

Once the construction during the intersection closure has been completed, there will be just a few more milestones left for the Van Ness Improvement Project before construction wraps up later this year. New overhead powerlines for transit lines will be installed. Additionally, crews will begin installing landscaping and irrigation systems, as well as pedestrian bulb-outs on sidewalks to aid in safer crossings for people walking.  

The project website details the available reroutes and provides additional information for motorists. While pedestrian access will be maintained at all times, people walking should consider bypassing the area. Transit will be rerouted, with Muni and AC Transit bus stops relocated and highly visible signage posted. Muni Metro and BART service will not be affected.

Once construction is complete, San Francisco’s first Bus Rapid Transit (BRT) system, a much needed and globally proven solution to improve transit service and address traffic congestion on Van Ness, is expected to begin operation in early 2022.   

In addition to the building of the BRT, the multi-agency Van Ness Improvement Project has also included the replacement of 1800s-era water main to better withstand a major earthquake, new streetlights that are more power-efficient and brighter, installation of the overhead contact system that provides 100% emissions-free hydroelectric power from Hetch Hetchy—the city's municipal power source—to power the buses, new landscape to beautify the corridor, and new pavement on Van Ness for smoother travel and sidewalk extensions for a safer experience for people walking. Completion of the project is in sight, with construction projected to finish by the end of the year.

The August 4-9 closure will impact people driving, biking, taking transit and walking in SoMa, Tenderloin, Civic Center, Hayes Valley, Downtown and Inner Mission. The South Van Ness and Mission Street intersection will be closed at all times, as well as the roads leading to the intersection. People who travel in the area are encouraged to “Scout Your Route” before the shutdown and plan their travel accordingly.

Thank you to all the residents and travelers who have remained patient through the traffic reroutes, dust and noise! We appreciate your support and are excited to welcome you on to the new BRT in early 2022. 



Published July 22, 2021 at 09:02AM
https://ift.tt/3wUq8j9

Comments

Popular posts from this blog

150 Years Ago Today – The Cable Car is Born

150 Years Ago Today – The Cable Car is Born By Kelley Trahan August 2, 2023, marks the 150th anniversary of the world’s first successful cable railway, born right here in San Francisco. To celebrate the occasion, we bring you the story of Andrew Hallidie and the very first cable car company, the Clay Street Hill Railroad.  Andrew Hallidie (1834-1900) was a pioneering inventor and entrepreneur who changed urban transportation. In 1852, at the age of 18, Hallidie emigrated with his father from the United Kingdom to San Francisco during the California Gold Rush. His father, an engineer and inventor, had a wire rope patent that played a crucial role in his son's future success.   Portrait of Andrew Smith Hallidie in 1890. Inspired by his father's wire rope business, Hallidie developed a steel cable mineral mine hauling system in 1857. About a decade later, he designed a wire rope aerial tramway for transporting materials over mountainous terrain. Then, after a stint in bridg...

Shared Spaces are Here to Stay. Permit Renewals are Due January 15, 2023.

Shared Spaces are Here to Stay. Permit Renewals are Due January 15, 2023. By Anne Yalon Shared Spaces, amongst many other benefits, allows our residents and families to enjoy safe and social outdoor dining. Seen here are the the owners of Tio Chilo’s Grill and their children in the restaurant’s parklet on 24th Street in the Mission.  San Francisco’s popular Shared Spaces program allows merchants, restaurants and arts and culture organizations to use the curbside, sidewalk and other public spaces to conduct local business activities and stay afloat. What emerged as an economic lifeline during the pandemic is making San Francisco’s streets more energized, engaged and activated. Many of the Shared Spaces parklets have become central gathering places for the local community. “ Our parklet makes me feel like when I go to Mexico, where outdoor seating is everywhere. People end up joining their friends in our parklet. It is a space for our customers and our community," said Liz V...

Tenderloin Streets Transform During COVID-19

Tenderloin Streets Transform During COVID-19 By Kimberly Leung COVID-19 has disproportionately impacted people who live and work in the Tenderloin. As a result, the SFMTA has been working closely with District 6 Supervisor Matt Haney’s office, other city departments, the Tenderloin Traffic Safety Task Force and community members to address the public health issues and unique challenges in the neighborhood through innovative interventions.    The Tenderloin is home to many of our most vulnerable communities including historically marginalized groups such as people with disabilities, residents of SROs and supportive housing and limited-English proficient communities. With every single street in the Tenderloin on the city’s High Injury Network -- the 13 percent of San Francisco streets that account for 75 percent of severe traffic injury collision and fatalities -- thi...